Capacity Curtailment on the NLL-GB-BE border for delivery period 21-11-2024
1. TSO(s)*:
Elia & NGESO
2. Identification of affected Long Term Transmission Rights:
NLL-GB-BE
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
21-11-2024 00:00 - 01:00 675 MW
21-11-2024 01:00 - 02:00 675 MW
21-11-2024 02:00 - 03:00 675 MW
21-11-2024 03:00 - 04:00 675 MW
21-11-2024 04:00 - 05:00 675 MW
21-11-2024 20:00 - 21:00 675 MW
21-11-2024 21:00 - 22:00 675 MW
21-11-2024 22:00 - 23:00 675 MW
21-11-2024 23:00 - 24:00 675 MW
5. Amount of LTTR remaining after curtailment:
21-11-2024 00:00 - 01:00 202 MW
21-11-2024 01:00 - 02:00 256 MW
21-11-2024 02:00 - 03:00 322 MW
21-11-2024 03:00 - 04:00 427 MW
21-11-2024 04:00 - 05:00 581 MW
21-11-2024 20:00 - 21:00 610 MW
21-11-2024 21:00 - 22:00 482 MW
21-11-2024 22:00 - 23:00 345 MW
21-11-2024 23:00 - 24:00 253 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets.
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
Reason for this curtailment is a forced outage on the cable 380.109 between the substations GEZEL380 and MAERL380.