Capacity Curtailment on the NLL-GB-BE border for delivery period 25-06-2025

Published:

1. TSO(s)*:

ELIA Transmission Belgium 

2. Identification of affected Long Term Transmission Rights:

NLL-GB-BE

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

25-06-2025 00:00 - 01:00 674 MW

25-06-2025 01:00 - 02:00 674 MW

25-06-2025 02:00 - 03:00 674 MW

5. Amount of LTTR remaining after curtailment:

25-06-2025 00:00 - 01:00 65 MW

25-06-2025 01:00 - 02:00 170 MW

25-06-2025 02:00 - 03:00 352 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets.

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

Reason for this curtailment is a forced outage on the cable 380.108 between the substations GEZEL380 and MAERL380.