Capacity Curtailment on the SI-AT border for delivery date 01-07-2024

Published:

1. TSO(s)*:

APG

2. Identification of affected Long Term Transmission Rights:

SI-AT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

01-07-2024 08:00 - 09:00 300 MW

01-07-2024 09:00 - 10:00 300 MW

5. Amount of LTTR remaining after curtailment:

01-07-2024 08:00 - 09:00 41 MW

01-07-2024 09:00 - 10:00 41 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets.

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication