Capacity Curtailment on the SI-AT border for delivery period 16-04-2025

Published:

1. TSO(s)*:

APG

2. Identification of affected Long Term Transmission Rights:

SI-AT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

16-04-2025 10:00 - 11:00 369 MW

16-04-2025 11:00 - 12:00 369 MW

16-04-2025 12:00 - 13:00 369 MW

16-04-2025 13:00 - 14:00 369 MW

16-04-2025 14:00 - 15:00 369 MW

16-04-2025 15:00 - 16:00 369 MW

16-04-2025 16:00 - 17:00 369 MW

5. Amount of LTTR remaining after curtailment:

16-04-2025 10:00 - 11:00 287 MW

16-04-2025 11:00 - 12:00 186 MW

16-04-2025 12:00 - 13:00 177 MW

16-04-2025 13:00 - 14:00 181 MW

16-04-2025 14:00 - 15:00 195 MW

16-04-2025 15:00 - 16:00 195 MW

16-04-2025 16:00 - 17:00 234 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets.

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication