Capacity Curtailment on the SI-IT border for delivery date 02-07-2024

Published:

1. TSO(s)*:

TERNA

2. Identification of affected Long Term Transmission Rights:

SI-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

02-07-2024 03:00 - 04:00 300 MW

02-07-2024 04:00 - 05:00 300 MW

02-07-2024 05:00 - 06:00 300 MW

02-07-2024 06:00 - 07:00 300 MW

02-07-2024 07:00 - 08:00 300 MW

02-07-2024 08:00 - 09:00 300 MW

5. Amount of LTTR remaining after curtailment:

02-07-2024 03:00 - 04:00 242 MW

02-07-2024 04:00 - 05:00 242 MW

02-07-2024 05:00 - 06:00 242 MW

02-07-2024 06:00 - 07:00 242 MW

02-07-2024 07:00 - 08:00 255 MW

02-07-2024 08:00 - 09:00 255 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets


7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication