Capacity Curtailment on the SI-IT border for delivery date 07-07-2024
1. TSO(s)*:
TERNA-ELES
2. Identification of affected Long Term Transmission Rights:
SI-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
07-07-2024 08:00 - 09:00 300 MW
07-07-2024 09:00 - 10:00 300 MW
07-07-2024 10:00 - 11:00 300 MW
07-07-2024 11:00 - 12:00 300 MW
07-07-2024 12:00 - 13:00 300 MW
07-07-2024 13:00 - 14:00 300 MW
07-07-2024 14:00 - 15:00 300 MW
07-07-2024 15:00 - 16:00 300 MW
07-07-2024 16:00 - 17:00 300 MW
07-07-2024 17:00 - 18:00 300 MW
07-07-2024 18:00 - 19:00 300 MW
07-07-2024 21:00 - 22:00 300 MW
07-07-2024 22:00 - 23:00 300 MW
07-07-2024 23:00 - 24:00 300 MW
5. Amount of LTTR remaining after curtailment:
07-07-2024 08:00 - 09:00 254 MW
07-07-2024 09:00 - 10:00 175 MW
07-07-2024 10:00 - 11:00 111 MW
07-07-2024 11:00 - 12:00 62 MW
07-07-2024 12:00 - 13:00 3 MW
07-07-2024 13:00 - 14:00 0 MW
07-07-2024 14:00 - 15:00 0 MW
07-07-2024 15:00 - 16:00 0 MW
07-07-2024 16:00 - 17:00 35 MW
07-07-2024 17:00 - 18:00 143 MW
07-07-2024 18:00 - 19:00 242 MW
07-07-2024 21:00 - 22:00 217 MW
07-07-2024 22:00 - 23:00 217 MW
07-07-2024 23:00 - 24:00 217 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.
*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication