Capacity Curtailment on the SI-IT border for delivery date 25-06-2024

Published:

1. TSO(s):
TERNA

2. Identification of affected Long Term Transmission Rights:

SI-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

25-06-2024 00:00 - 01:00 379 MW

25-06-2024 01:00 - 02:00 379 MW

25-06-2024 02:00 - 03:00 379 MW

25-06-2024 03:00 - 04:00 379 MW

25-06-2024 04:00 - 05:00 379 MW

25-06-2024 05:00 - 06:00 379 MW

25-06-2024 06:00 - 07:00 379 MW

25-06-2024 07:00 - 08:00 379 MW

25-06-2024 08:00 - 09:00 379 MW

25-06-2024 18:00 - 19:00 379 MW

25-06-2024 19:00 - 20:00 379 MW

25-06-2024 20:00 - 21:00 379 MW

25-06-2024 21:00 - 22:00 379 MW

25-06-2024 22:00 - 23:00 379 MW

25-06-2024 23:00 - 24:00 379 MW

5. Amount of LTTR remaining after curtailment:

25-06-2024 00:00 - 01:00 155 MW

25-06-2024 01:00 - 02:00 155 MW

25-06-2024 02:00 - 03:00 155 MW

25-06-2024 03:00 - 04:00 327 MW

25-06-2024 04:00 - 05:00 327 MW

25-06-2024 05:00 - 06:00 327 MW

25-06-2024 06:00 - 07:00 327 MW

25-06-2024 07:00 - 08:00 179 MW

25-06-2024 08:00 - 09:00 179 MW

25-06-2024 18:00 - 19:00 190 MW

25-06-2024 19:00 - 20:00 190 MW

25-06-2024 20:00 - 21:00 190 MW

25-06-2024 21:00 - 22:00 215 MW

25-06-2024 22:00 - 23:00 215 MW

25-06-2024 23:00 - 24:00 191 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment:
Expected violation of operational security limits of physical transmission assets

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication