Capacity Curtailment on the SI-IT border for delivery day 12/07/2020

Published:

1. TSO(s) *: TERNA

2. Identification of affected Long Term Transmission Rights

Slovenia to Italy

3. Triggering event:

☐Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation

4. Affected volume in MW / hour for each concerned period:

Slovenia to Italy

12/07/2020

00:00 – 01:00 221 MW

01:00 – 02:00 221 MW

02:00 – 03:00 221 MW

03:00 – 04:00 221 MW

04:00 – 05:00 221 MW

05:00 – 06:00 221 MW

06:00 – 07:00 221 MW

07:00 – 08:00 221 MW

08:00 – 09:00 221 MW

09:00 – 10:00 221 MW

10:00 – 11:00 221 MW

11:00 – 12:00 221 MW

12:00 – 13:00 221 MW

13:00 – 14:00 221 MW

14:00 – 15:00 221 MW

15:00 – 16:00 221 MW

16:00 – 17:00 221 MW

17:00 – 18:00 221 MW

18:00 – 19:00 221 MW

19:00 – 20:00 221 MW

20:00 – 21:00 221 MW

21:00 – 22:00 221 MW

22:00 – 23:00 221 MW

23:00 – 24:00 221 MW

5. Amount of LTTR remaining after curtailment:

Slovenia to Italy

12/07/2020

00:00 – 01:00 221 MW

01:00 – 02:00 221 MW

02:00 – 03:00 221 MW

03:00 – 04:00 221 MW

04:00 – 05:00 221 MW

05:00 – 06:00 198 MW

06:00 – 07:00 198 MW

07:00 – 08:00 221 MW

08:00 – 09:00 221 MW

09:00 – 10:00 221 MW

10:00 – 11:00 221 MW

11:00 – 12:00 170 MW

12:00 – 13:00 93 MW

13:00 – 14:00 93 MW

14:00 – 15:00 73 MW

15:00 – 16:00 87 MW

16:00 – 17:00 176 MW

17:00 – 18:00 221 MW

18:00 – 19:00 221 MW

19:00 – 20:00 221 MW

20:00 – 21:00 221 MW

21:00 – 22:00 221 MW

22:00 – 23:00 221 MW

23:00 – 24:00 221 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Voltage stability issue on the Italian Electrical system

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation