Capacity Curtailment on the SI-IT border for delivery day 06/06/2020
1. TSO(s) *: TERNA
2. Identification of affected Long Term Transmission Rights
Slovenia to Italy
3. Triggering event :
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
4. Affected volume in MW / hour for each concerned period :
Slovenia to Italy
06/06/2020
§ 12:00 – 13:00 49 MW
§ 13:00 – 14:00 49 MW
§ 14:00 – 15:00 49 MW
§ 15:00 – 16:00 49 MW
5. Amount of LTTR remaining after curtailment :
Slovenia to Italy
06/06/2020
§ 12:00 – 13:00 0 MW
§ 13:00 – 14:00 0 MW
§ 14:00 – 15:00 0 MW
§ 15:00 – 16:00 0 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *: Voltage stability issue on the Italian Electrical system.
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *? During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.