Capacity Curtailment on the SI-IT border for delivery day 22/11/2020
1. TSO(s) *: TERNA, RTE, Swissgrid, APG, ELES
2. Identification of affected Long Term Transmission Rights
Slovenia to Italy
3. Triggering event:
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
4. Affected volume in MW / hour for each concerned period:
Slovenia to Italy
22/11/2020
00:00 – 01:00 362 MW
01:00 – 02:00 362MW
02:00 – 03:00 362MW
03:00 – 04:00 362MW
04:00 – 05:00 362MW
05:00 – 06:00 362MW
06:00 – 07:00 362MW
07:00 – 08:00 362MW
08:00 – 09:00 362MW
09:00 – 10:00 362MW
10:00 – 11:00 362MW
11:00 – 12:00 362MW
12:00 – 13:00 362MW
13:00 – 14:00 362MW
14:00 – 15:00 362MW
15:00 – 16:00 362MW
16:00 – 17:00 362MW
17:00 – 18:00 362MW
18:00 – 19:00 362MW
19:00 – 20:00 362MW
20:00 – 21:00 362MW
21:00 – 22:00 362MW
22:00 – 23:00 362MW
23:00 – 24:00 362MW
5. Amount of LTTR remaining after curtailment:
Slovenia to Italy
22/11/2020
00:00 – 01:00 362MW
01:00 – 02:00 362MW
02:00 – 03:00 362MW
03:00 – 04:00 326MW
04:00 – 05:00 326MW
05:00 – 06:00 326MW
06:00 – 07:00 326MW
07:00 – 08:00 362MW
08:00 – 09:00 362MW
09:00 – 10:00 362MW
10:00 – 11:00 362MW
11:00 – 12:00 362MW
12:00 – 13:00 362MW
13:00 – 14:00 362MW
14:00 – 15:00 362MW
15:00 – 16:00 362MW
16:00 – 17:00 362MW
17:00 – 18:00 362MW
18:00 – 19:00 362MW
19:00 – 20:00 362MW
20:00 – 21:00 362MW
21:00 – 22:00 362MW
22:00 – 23:00 362MW
23:00 – 24:00 362MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
For period
03:00 – 04:00 326MW
04:00 – 05:00 326MW
05:00 – 06:00 326MW
06:00 – 07:00 326MW
Reduction due to the following overloaded element(s): Lienz - Soverzene
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation