Capacity Curtailment on the SI-IT border for delivery day 25/05/2021

Published:

1. TSO(s) *: TERNA, ELES

2. Identification of affected Long Term Transmission Rights

Slovenia to Italy

3. Triggering event:

 

☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
 

4. Affected volume in MW / hour for each concerned period:

Slovenia to Italy

25/05/2021  

 

08:00 – 09:00  302 MW

09:00 – 10:00  302 MW

10:00 – 11:00  302 MW

11:00 – 12:00  302 MW

 

5. Amount of LTTR remaining after curtailment:

Slovenia to Italy

25/05/2021  

 

08:00 – 09:00  174 MW

09:00 – 10:00  0 MW

10:00 – 11:00  0 MW

11:00 – 12:00  159 MW

 

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Hour 08:00 – 09:00: Entrance ramp to reduction;

Hour  09:00 – 10:00 and 10:00 – 11:00:  Reduction due to the unavailability of 400 kV TL Divaca-Redipuglia;

Hour 11:00 – 12:00 : Exit ramp from reduction.

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation