Capacity Curtailment on the SI-IT border for delivery day 09/12/2021
1.TSO(s) *:
2. Identification of affected Long Term Transmission Rights
Slovenia to Italy
3. Triggering event:
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
4. Affected volume in MW / hour for each concerned period:
Slovenia to Italy
09/12/2021
02:00 – 03:00 363MW
03:00 – 04:00 363MW
04:00 – 05:00 363MW
5. Amount of LTTR remaining after curtailment:
Slovenia to Italy
09/12/2021
02:00 – 03:00 313 MW
03:00 – 04:00 298 MW
04:00 – 05:00 329 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?