Capacity Curtailment on the SI-IT border for delivery day 27/12/2021
1. TSO(s) *:
APG-RTE-ELES-SWG
2. Identification of affected Long Term Transmission Rights
Slovenia to Italy
3. Triggering event :
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
4. Affected volume in MW / hour for each concerned period :
Slovenia to Italy
27/12/2021
00:00 – 01:00 222 MW
01:00 – 02:00 222 MW
02:00 – 03:00 222 MW
03:00 – 04:00 222 MW
04:00 – 05:00 222 MW
05:00 – 06:00 222 MW
06:00 – 07:00 222 MW
07:00 – 08:00 222 MW
08:00 – 09:00 222 MW
09:00 – 10:00 222 MW
10:00 – 11:00 222 MW
11:00 – 12:00 222 MW
12:00 – 13:00 222 MW
13:00 – 14:00 222 MW
14:00 – 15:00 222 MW
15:00 – 16:00 222 MW
16:00 – 17:00 222 MW
17:00 – 18:00 222 MW
18:00 – 19:00 222 MW
19:00 – 20:00 222 MW
20:00 – 21:00 222 MW
21:00 – 22:00 222 MW
22:00 – 23:00 222 MW
23:00 – 24:00 222 MW
5. Amount of LTTR remaining after curtailment :
Slovenia to Italy
27/12/2021
00:00 – 01:00 222 MW
01:00 – 02:00 222 MW
02:00 – 03:00 181 MW
03:00 – 04:00 181 MW
04:00 – 05:00 181 MW
05:00 – 06:00 222 MW
06:00 – 07:00 222 MW
07:00 – 08:00 222 MW
08:00 – 09:00 222 MW
09:00 – 10:00 222 MW
10:00 – 11:00 222 MW
11:00 – 12:00 222 MW
12:00 – 13:00 222 MW
13:00 – 14:00 222 MW
14:00 – 15:00 222 MW
15:00 – 16:00 222 MW
16:00 – 17:00 222 MW
17:00 – 18:00 222 MW
18:00 – 19:00 222 MW
19:00 – 20:00 222 MW
20:00 – 21:00 222 MW
21:00 – 22:00 222 MW
22:00 – 23:00 222 MW
23:00 – 24:00 222 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Possible violations on the line Soverzene-Lienz
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.