Capacity Curtailment on the SI-IT border for delivery day 21/07/2022

Published:

1.TSO(s) *:

Swissgrid

2. Identification of affected Long Term Transmission Rights

Slovenia to Italy

3. Triggering event:

 

☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
 

4. Affected volume in MW / hour for each concerned period:

Slovenia to Italy

21/07/2022  

 

07:00 – 08:00  389MW

08:00 – 09:00  389MW

09:00 – 10:00  389MW

10:00 – 11:00  389MW

11:00 – 12:00  389MW

12:00 – 13:00  389MW

13:00 – 14:00  389MW

14:00 – 15:00  389MW

15:00 – 16:00  389MW

16:00 – 17:00  389MW

17:00 – 18:00  389MW

18:00 – 19:00  389MW

19:00 – 20:00  389MW

20:00 – 21:00  389MW

21:00 – 22:00  389MW

22:00 – 23:00  389MW

23:00 – 24:00  389MW

 

5. Amount of LTTR remaining after curtailment:

Slovenia to Italy

21/07/2022  

07:00 – 08:00  315MW

08:00 – 09:00  315MW

09:00 – 10:00  345MW

10:00 – 11:00  345MW

11:00 – 12:00  345MW

12:00 – 13:00  323MW

13:00 – 14:00  323MW

14:00 – 15:00  323MW

15:00 – 16:00  345MW

16:00 – 17:00  345MW

17:00 – 18:00  345MW

18:00 – 19:00  314MW

19:00 – 20:00  314MW

20:00 – 21:00  314MW

21:00 – 22:00  290MW

22:00 – 23:00  290MW

23:00 – 24:00  249MW

 

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

 Expected overloading on 380kV Sils – Soazza;  Robbia-Gorlago + Robbia-S.Fiorano

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

 During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.