Capacity Curtailment on the SI-IT border for delivery day 22/07/2022

Published:

1. TSO(s) *:

2. Identification of affected Long Term Transmission Rights

Slovenia to Italy

3. Triggering event:

☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
 

4. Affected volume in MW / hour for each concerned period:

Slovenia to Italy

22/07/2022  

00:00 – 01:00  389MW

01:00 – 02:00  389MW

02:00 – 03:00  389MW

03:00 – 04:00  389MW

04:00 – 05:00  389MW

05:00 – 06:00  389MW

06:00 – 07:00  389MW

07:00 – 08:00  389MW

08:00 – 09:00  389MW

09:00 – 10:00  389MW

10:00 – 11:00  389MW

11:00 – 12:00  389MW

12:00 – 13:00  389MW

13:00 – 14:00  389MW

14:00 – 15:00  389MW

15:00 – 16:00  389MW

16:00 – 17:00  389MW

17:00 – 18:00  389MW

23:00 – 24:00  389MW

5. Amount of LTTR remaining after curtailment:

Slovenia to Italy

22/07/2022  

00:00 – 01:00  348MW

01:00 – 02:00  348MW

02:00 – 03:00  348MW

03:00 – 04:00  261MW

04:00 – 05:00  261MW

05:00 – 06:00  261MW

06:00 – 07:00  261MW

07:00 – 08:00  322MW

08:00 – 09:00  322MW

09:00 – 10:00  322MW

10:00 – 11:00  322MW

11:00 – 12:00  318MW

12:00 – 13:00  318MW

13:00 – 14:00  318MW

14:00 – 15:00  389MW

15:00 – 16:00  389MW

16:00 – 17:00  362MW

17:00 – 18:00  362MW

23:00 – 24:00  335MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Expected overloading on 380kV Sils – Soazza; Robbia-Gorlago + Robbia-S.Fiorano

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.