Capacity Curtailment on the SI-IT border for delivery day 20/11/2022
1. TSO(s) *: ELES, TERNA, RTE, Swissgrid Violation on Lienz – Soverzene due to Critical outage DIVACA-REDIPUGLIA/DIVACA-PADRICIANO
2. Identification of affected Long Term Transmission Rights
Slovenia to Italy
3. Triggering event:
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
4. Affected volume in MW / hour for each concerned period:
Slovenia to Italy
20/11/2022
01:00 – 02:00 420 MW
02:00 – 03:00 420 MW
03:00 – 04:00 420 MW
04:00 – 05:00 420 MW
5. Amount of LTTR remaining after curtailment:
Slovenia to Italy
20/11/2022
01:00 – 02:00 375 MW
02:00 – 03:00 370 MW
03:00 – 04:00 355 MW
04:00 – 05:00 355 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Violation on Lienz – Soverzene due to Critical outage DIVACA-REDIPUGLIA/DIVACA-PADRICIANO
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation