Capacity Curtailment on the SI-IT border for delivery period 04-07-2025

Published:

1. TSO(s)*:

TERNA

2. Identification of affected Long Term Transmission Rights:

SI-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

04-07-2025 18:00 - 19:00 248 MW

04-07-2025 23:00 - 24:00 248 MW

5. Amount of LTTR remaining after curtailment:

04-07-2025 18:00 - 19:00 207 MW

04-07-2025 23:00 - 24:00 214 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

 

Expected violation of operational security limits of physical transmission assets

 

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

 

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC