Capacity Curtailment on the SI-IT border for delivery period 19-11-2024
1. TSO(s)*:
TERNA, ELES
2. Identification of affected Long Term Transmission Rights:
SI-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
19-11-2024 12:00 - 13:00 426 MW
19-11-2024 13:00 - 14:00 426 MW
19-11-2024 14:00 - 15:00 426 MW
19-11-2024 18:00 - 19:00 426 MW
19-11-2024 19:00 - 20:00 426 MW
19-11-2024 20:00 - 21:00 426 MW
5. Amount of LTTR remaining after curtailment:
19-11-2024 12:00 - 13:00 252 MW
19-11-2024 13:00 - 14:00 252 MW
19-11-2024 14:00 - 15:00 252 MW
19-11-2024 18:00 - 19:00 328 MW
19-11-2024 19:00 - 20:00 370 MW
19-11-2024 20:00 - 21:00 327 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation