Capacity Curtailment on the SI-IT border for delivery period 20-11-2024

Published:

1. TSO(s)*:

TERNA, ELES

2. Identification of affected Long Term Transmission Rights:

SI-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

20-11-2024 07:00 - 08:00 426 MW

20-11-2024 08:00 - 09:00 426 MW

20-11-2024 15:00 - 16:00 426 MW

20-11-2024 16:00 - 17:00 426 MW

20-11-2024 17:00 - 18:00 426 MW

5. Amount of LTTR remaining after curtailment:

20-11-2024 07:00 - 08:00 370 MW

20-11-2024 08:00 - 09:00 370 MW

20-11-2024 15:00 - 16:00 327 MW

20-11-2024 16:00 - 17:00 376 MW

20-11-2024 17:00 - 18:00 376 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation