Capacity Curtailment on the SI-IT border for delivery period 27-11-2024
1. TSO(s)*:
2. Identification of affected Long Term Transmission Rights:
SI-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
27-11-2024 18:00 - 19:00 426 MW
27-11-2024 19:00 - 20:00 426 MW
27-11-2024 20:00 - 21:00 426 MW
5. Amount of LTTR remaining after curtailment:
27-11-2024 18:00 - 19:00 307 MW
27-11-2024 19:00 - 20:00 353 MW
27-11-2024 20:00 - 21:00 353 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication