Capacity Curtailment on the SI-IT border for delivery period 22-01-2025
1. TSO(s)*:
TERNA
2. Identification of affected Long Term Transmission Rights:
SI-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
22-01-2025 09:00 - 10:00 318 MW
22-01-2025 10:00 - 11:00 318 MW
22-01-2025 11:00 - 12:00 318 MW
22-01-2025 12:00 - 13:00 318 MW
22-01-2025 13:00 - 14:00 318 MW
22-01-2025 14:00 - 15:00 318 MW
5. Amount of LTTR remaining after curtailment:
22-01-2025 09:00 - 10:00 281 MW
22-01-2025 10:00 - 11:00 281 MW
22-01-2025 11:00 - 12:00 281 MW
22-01-2025 12:00 - 13:00 257 MW
22-01-2025 13:00 - 14:00 257 MW
22-01-2025 14:00 - 15:00 257 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication