Capacity Curtailment on the SI-IT border for delivery period 25-04-2025
1. TSO(s)*:
TERNA, ELES
2. Identification of affected Long Term Transmission Rights:
SI-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
25-04-2025 10:00 - 11:00 66 MW
25-04-2025 11:00 - 12:00 66 MW
25-04-2025 12:00 - 13:00 66 MW
25-04-2025 13:00 - 14:00 66 MW
25-04-2025 14:00 - 15:00 66 MW
25-04-2025 15:00 - 16:00 66 MW
25-04-2025 16:00 - 17:00 66 MW
5. Amount of LTTR remaining after curtailment:
25-04-2025 10:00 - 11:00 0 MW
25-04-2025 11:00 - 12:00 0 MW
25-04-2025 12:00 - 13:00 0 MW
25-04-2025 13:00 - 14:00 0 MW
25-04-2025 14:00 - 15:00 0 MW
25-04-2025 15:00 - 16:00 0 MW
25-04-2025 16:00 - 17:00 0 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment:
Expected violation of operational security limits of physical transmission assets
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC