The long-term allocated capacity for delivery date 08/02/2018 on the corridors from Slovenia to Italy, from France to Italy and from Austria to Italy has been curtailed to ensure operation remains within Operational Security Limits.
SI-IT
From position 04 to 06 reduced to 335 MW
FR-IT
On position 03 reduced to 2242 MW
From position 04 to 06 reduced to 1617 MW
On position 07 reduced to 2242 MW
From position 22 to 23 reduced to 2294 MW
On position 24 reduced to 2430 MW
AT-IT
From position 04 to 06 reduced to 196 MW