Capacity Curtailment from Switzerland to Italy, and from Austria to Italy for delivery date 28/11/2018
Dear Market Participants,
The long-term allocated capacities for delivery date 28/11/2018 on the corridors from Switzerland to Italy, and from Austria to Italy have been curtailed to ensure operation remains within Operational Security Limits.
CH>IT:
From Position 1 to position 3 was reduced by 1%
From Position 4 to position 7 was reduced by 6%
From Position 9 to position 17 was reduced by 21%
On position 18 it was reduced by 19%
On position 19 it was reduced by 20%
On position 20 it was reduced by 21%
On position 24 it was reduced by 1%
AT>IT:
On position 6 it was reduced to 192 MW
On position 7 it was reduced to 135 MW
From Position 8 to Position 18 was reduced to 73 MW
On position 19 it was reduced to 135 MW
On position 20 it was reduced to 192 MW
Please consider the latest version of the programming authorizations.
Best regards,
Operations Team
JAO S.A.