Capacity Curtailment from Switzerland to Italy, and from France to Italy for delivery date 17/01/2019
Dear Market Participants,
The long-term allocated capacities for delivery date 17/01/2019 on the corridor from Switzerland to Italy, and from France to Italy have been curtailed to ensure operation remains within Operational Security Limits.
CH-IT:
From position 1 to 7 it was reduced by 3%
From position 9 to 17 it was reduced by 4%
On position 24 it was reduced by 3%
FR-IT:
From position 1 to 7 it was reduced to 2015 MW
From position 8 to 17 it was reduced to 2403 MW
From position 18 to 21 it was reduced to 2337 MW
From position 22 to 23 it was reduced to 1875 MW
Position 24 was reduced to 2015 MW
Please consider the latest version of the programming authorizations.
Kind regards,
Operations Team
JAO S.A.
2 rue de Bitbourg
L-1273 Luxembourg-Hamm
T. +352 27 62 38 38