Capacity Curtailment from Switzerland/France to Italy for delivery date 29/12/2017
Dear Market Participants,
The long-term allocated capacity for delivery date 29/12/2017 on the corridor from Switzerland to Italy has been curtailed to ensure operation remains within Operational Security Limits.
CH>IT:
On position 9 reduced by 11%
From position 10 to position 12 reduced by 18%
From position 13 to position 15 reduced by 17%
The long-term allocated capacity for delivery date 29/12/2017 on the corridor from France to Italy has been curtailed to ensure operation remains within Operational Security Limits.
FR>IT:
From position 1 to position 3 reduced to 2233 MW
On position 7 reduced to 2293 MW
From position 8 to position 9 reduced to 2168 MW
From position 10 to position 12 reduced to 2016 MW
From position 13 to position 15 reduced to 2033 MW
From position 16 to position 18 reduced to 2461 MW
Please remember to use version 2 of the programming authorizations.
Best regards,
Operations Team
JAO S.A.