Capacity Curtailment on the VKL-D1-GB border for delivery period 09-01-2025

Published:

1. TSO(s)*:

RNP

2. Identification of affected Long Term Transmission Rights:

VKL-GB-D1

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

09-01-2025 17:00 - 18:00 600 MW

5. Amount of LTTR remaining after curtailment:

09-01-2025 17:00 - 18:00 0 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Thermal Limits

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
Capacity limitation due to planned maintenance

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication