Capacity Curtailment on the VKL-D1-GB border for delivery period 12-08-2025

Published:

1. TSO(s)*:

National Grid Viking Link Limited (NGVLL) and Energinet

2. Identification of affected Long Term Transmission Rights:

VKL-D1-GB

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

12-08-2025 11:00 - 12:00 550 MW

12-08-2025 12:00 - 13:00 550 MW

5. Amount of LTTR remaining after curtailment:

12-08-2025 11:00 - 12:00 0 MW

12-08-2025 12:00 - 13:00 0 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Thermal Limits

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

Capacity limitation due to planned maintenance