Capacity Curtailments on DE-NL, AT-IT and FR-IT borders for delivery day 19/11/2019
Dear Market Participants,
The long-term allocated capacities for delivery day 19th of November 2019 on the corridor from Germany to the Netherlands, from Austria to Italy and from France to Italy have been curtailed to ensure operation remains within Operational Security Limits.
DE>NL
On position 10 it was reduced to 989 MW
From position 11 to position 12 it was reduced to 977 MW
From position 13 to position 15 it was reduced to 981 MW
On position 16 it was reduced to 1007 MW
On position 17 it was reduced to 1010 MW
AT>IT
From position 1 to position 7 it was reduced to 78 MW
On Position 24 it was reduced to 78 MW
FR>IT
From position 1 to position 7 it was reduced to 1888 MW
On position 8 it was reduced to 2384 MW
On position 24 it was reduced to 2289 MW
Please consider the latest version of the programming authorizations.
Best regards,
Operations Team