Capacity Curtailments on the FR-IT and CH-IT borders for delivery day 01/12/2019
Dear Market Participants,
The long-term allocated capacities for delivery day 1st of December 2019 on the corridor from France to Italy, and from Switzerland to Italy have been curtailed to ensure operation remains within Operational Security Limits.
FR>IT
From position 1 to 7 it was reduced to 1851 MW
On position 8 it was reduced to 2309 MW
On position 9 it was reduced to 2378 MW
From position 10 to 12 it was reduced to 2403 MW
From position 13 to 15 it was reduced to 2378 MW
From position 22 to 24 it was reduced to 2393 MW
CH>IT
From position 1 to 7 it was reduced by 2%
Please consider the latest version of the programming authorizations.