[CORE DA FB MC / CORE IDCC] Commissioning of new 380 kV lines Buerstadt – Lambsheim BUERSTADT OST and Lambsheim – Maximiliansau WEINSTRASSE OST
Dear Market Participants,
Amprion GmbH is expecting the commissioning of the new 380 kV lines
BUERSTADT OST between Buerstadt and Lambsheim substations on 14/08/2024 and
WEINSTRASSE OST between Lambsheim and Maximiliansau substations on 16/08/2024.
This will result in the addition of the following CNEs to Core DA FB MC and Core IDCC starting on business day 14/08/2024:
|
CNE Publication Name |
EIC Code |
Imax [A] |
|
[D7-D7] Buerstadt – Lambsheim BUERST O |
11T0-0000-2121-0 |
2720 |
|
[D7-D7] Lambsheim – Maximiliansau WEINST O |
11T0-0000-2119-H |
2720 |
The associated CNECs are listed in the attached excel sheet.
The 220 kV line [D7-D7] Buerstadt – Maximiliansau WEINGT (EIC Code 11T0-0000-0359-3) will be decommissioned and the associated CNECs removed from Core DA FB MC and Core IDCC.
Best regards,
Amprion GmbH