[CORE DA FB MC / CORE IDCC] Commissioning of new lines Daxlanden – Maximiliansau GOLDGRUND OST and Daxlanden – Mutterstadt BIENWALD WEST
Dear Market Participants,
TransnetBW GmbH and Amprion GmbH are expecting the commissioning of the new 380 kV line
GOLDGRUND OST between Daxlanden and Maximiliansau substations on 30/09/2024
and the new 220 kV line
BIENWALD WEST between Daxlanden and Mutterstadt substations on 01/10/2024.
This will result in the addition of the following CNEs to Core DA FB MC and Core IDCC starting on business day 30/09/2024:
CNE Publication Name |
EIC Code |
Imax [A] |
[D4-D7] Daxlanden – Maximiliansau GOLDGR O |
11T0-0000-2263-A |
2720 |
[D4-D7] Daxlanden – Mutterstadt BIENWD W |
11T0-0000-2262-D |
1360 |
The associated CNECs are listed in the attached excel sheet.
The CNE [D4-D7] Daxlanden – Maximiliansau GOLDGR (EIC Code 11T-D4-D7-00002U) will be decommissioned and the associated CNECs removed from Core DA FB MC and Core IDCC.
Best regards,
TransnetBW GmbH
Amprion GmbH