RTE would like to inform you that reductions of the admissible transmission loadings on the critical branch Avelin-Avelgem 400kV due to unplanned works are extended.
The Imax value of 700A, will be applicable for following hours (CET):
- 23/05/22 14h-18h
- 24/05/22 08h-12h and 14h-18h
- 25/05/22 08h-12h and 14h-18h
- 26/05/22 08h-12h and 14h-18h
- 27/05/22 08h-12h
- 30/05/22 14h-18h
- 31/05/22 08h-12h and 14h-18h
- 01/06/22 08h-12h and 14h-18h
- 02/06/22 08h-12h and 14h-18h
- 03/06/22 08h-12h
- 06/06/22 14h-18h
- 07/06/22 08h-12h and 14h-18h
- 08/06/22 08h-12h and 14h-18h
- 09/06/22 08h-12h and 14h-18h
- 10/06/22 08h-12h
- 13/06/22 14h-18h
- 14/06/22 08h-12h and 14h-18h
- 15/06/22 08h-12h and 14h-18h
- 16/06/22 08h-12h
Further details are published on RTE’s customer portal.
We will keep you informed if further information is available.
Best Regards,
RTE - Réseau de Transport d’électricité S.A