[CWE Flow-Based Market Coupling] Changes in External Constraints for the Belgian bidding zone

Published:

Dear Market Participants,

from business day Friday the 1st of June 2018 onwards, Elia System Operator S.A. will adapt the External Constraint value for import from 4500 MW to 5500 MW for the Belgian bidding zone.

This change is valid for all time stamps and all days. This change will be applied from delivery day 01/06/2018 (day-ahead market coupling 31/05/2018) for the CWE day-ahead Flow-Based market coupling.

Best regards,