DA NTC on Nemo Link (GB to BE direction) delivery 12/12/2024

Published:

Dear Market Participant,

Please be advised that the DA NTC (Net Transfer Capacity) on the Nemo Link Interconnector, direction GB to BE, for delivery 12/12/2024 between 10:00 and 20:00 (CET) were set at 0 MW due to incorrect DA NTC values submitted by NESO.

As a result, the offered capacity in the DA auction for the above period were lower than otherwise it would have been. Non-nominated Long-Term Transmission Rights for the impacted period if curtailed will be compensated at the Loss-Adjusted Day Ahead Market Spread in accordance to the Nemo Link’s Access Rules.

We apologies for any inconvenience that this may have caused. For further assistance, please do not hestitate to contact us at customer.service@nemolink.co.uk. 

Kind regards,

Nemo Link Customer Team