EL1 FR<>GB LT Rights Curtailment

Published:

LT Right Curtailment Required for Delivery Date(s):

21:00 19/07/2025 - 09:00 20/07/2025

1. TSO(s):

ElecLink

2. Identification of affected Long Term Transmission Rights:

ElecLink FR<>GB

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

All long-term capacity is affected for delivery date(s)

5. Amount of LTTR remaining after curtailment:

0MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment:

Planned Outage

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)?:

Maintenance for a Planned outage