Maintenance Period September 2022 Monthly ATC DE->FR
Dear Market Participants,
The German transmission system operator Amprion GmbH would like to inform you that the capacity for the September 2022 monthly auction from September 19, 2022 to September 30, 2022 between Germany and France in the direction from Germany to France will only be 260 MW as a maintenance period. For the remaining month the monthly auction remains at 400 MW.
Due to special outages that must be carried out at the same time during the September 19, 2022 and September 30, 2022 in the Bürstadt area, the network situation will become significantly more tense. In order to maintain network security, we therefore consider the reduction in monthly capacity to be necessary.