RE: Capacity Curtailment from Switzerland/France/Austria to Italy for delivery date 28/12/2017
Dear Market Participants,
The long-term allocated capacity for delivery date 28/12/2017 on the corridor from Switzerland to Italy has been curtailed to ensure operation remains within Operational Security Limits.
CH>IT:
On position 9 reduced by 3%
From position 10 to position 12 reduced by 29%
From position 13 to position 15 reduced by 4%
The long-term allocated capacity for delivery date 28/12/2017 on the corridor from France to Italy has been curtailed to ensure operation remains within Operational Security Limits.
FR>IT:
From position 8 to position 9 reduced to 2359 MW
From position 10 to position 12 reduced to 1773 MW
From position 13 to position 15 reduced to 2328 MW
From position 22 to position 23 reduced to 2139 MW
On position 24 reduced to 2263 MW
The long-term allocated capacity for delivery date 28/12/2017 on the corridor from Austria to Italy has been curtailed to ensure operation remains within Operational Security Limits.
AT>IT:
From position 10 to position 12 reduced to 214 MW
Please remember to use version 2 of the programming authorizations for nomination purpose.
Best regards,
Operations Team
JAO S.A.