RTE and SWISSGRID announce Yearly 2025 auction on the FR<>CH border 11-09-2024
Dear market participants,
In line with a request from the French regulator CRE and after a public consultation which gathered Market Participants’ views, RTE and Swissgrid are pleased to announce that the France-Switzerland annual capacity for the delivery year 2025 will be split and offered into two separate auctions: the first one will be held in September 2024 and the second one end of Q4 2024.
The details of the second auction (end of Q4) will be communicated at a later stage.
As for the September auction, you will find the details below (timings in CET):
Bidding Month |
Interconnector |
Product |
Horizon |
Volume (MW) |
Auction Start |
Time (of the opening) |
Auction End |
Time (of the End) |
Dispute period |
September 2024 |
CH->FR |
Y BASE 1 |
2025 |
50 |
11/09/2024 |
13:30 |
18/09/2024 |
13:30 |
2-2 days |
September 2024 |
FR->CH |
Y BASE 1 |
2025 |
185 |
11/09/2024 |
13:30 |
18/09/2024 |
13:30 |
2-2 days |