Split of the FR<>BE annual 2025 auction
Dear Market Participants,
We would like to inform you that following a successful auction split in 2023, RTE and Elia are pleased to announce that the France-Belgium annual capacity for the delivery year 2025 will be split and offered into two separate auctions. The first one will be held in September 2024 and the second one end of Q4 2024.
As for the September auction, you will find the details below (timings in CET):
Bidding Month |
Interconnector |
Product |
Horizon |
Volume (MW) |
Auction Start |
Time (of the opening) |
Auction End |
Time (of the End) |
Dispute period |
September 2024 |
BE->FR |
Y BASE 1 |
2025 |
125 |
10/09/2024 |
13:50 |
12/09/2024 |
13:50 |
2-2 days |
September 2024 |
FR->BE |
Y BASE 1 |
2025 |
700 |
10/09/2024 |
13:50 |
12/09/2024 |
13:50 |
2-2 days |
The details of the second auction (end of Q4) will be communicated at a later stage.
Kind Regards,
JAO Operations