Update LTA curtailment from Germany to Belgium applied by Elia Transmission Belgium

Published:

This above LTA curtailment is cancelled 

Dear Market Participants,

In order to ensure a safe operation of the grid, curtailment will be applied on the allocated Long-Term Transmission Rights from Germany to Belgium for the following period and amount:

-          Business day Sunday May 16th, 2021 for hours 00h00 – 24h00

-          NTC reduced from 400MW to 0MW (meaning a reduction of 400MW)

In accordance with Harmonized Allocation Rules, market participants will be compensated.

We do our best to limit the impact for the market and will keep you informed if any relevant update.

Best regards,

Elia Transmission Belgium