[TTN] Commissioning of third MEE PST

Published:

Dear Market Participants,

 

This is an update on the previous Meeden Phase Shift Transformers message: https://www.jao.eu/news/ttn-restrictions-mee-psts

 

The third PST has been commissioned on the MEE-DIL interconnector. The PST is expected to be in service from businessday June 10, 2024 and has been added as a CNE with the appropriate CO's in the flowbased domains of the Day-ahead and Intraday Capacity Calculation processes. Both other PSTs remain in outage until further notice, pending repairs.

 

We trust to have informed you sufficiently.

 

Sincerely,

 

TenneT TSO B.V.